ECC approves Rs24.5bn for solarization of Agri tube-wells in Balochistan
May 05, 2025

The Economic Coordination Committee has approved release of 24.5 billion rupees for timely completion of the project for solarization of 27,000 agri tube-wells in Balochistan.              

The approval was granted at a meeting of ECC held in Islamabad today, with Finance Minister Muhammad Aurangzeb in the chair.                  

The project will be completed at a cost of 55 billion rupees jointly by the federal government and provincial government of Balochistan with the financing ratio of 70 and 30 percent respectively. The ECC was told that an amount of 14 billion rupees was already released.              

The ECC directed the Power Division to closely monitor implementation of the project, particularly the disconnection of tubewells from the grid and removal of transformers and fixtures for every batch of feeders, as agreed under the project.

The ECC also directed the Power Division to report the progress on this account in July.

During the meeting, the ECC was briefed by the Power Division about power distribution companies, that Board of Directors of al DISCOs have been reconstituted and a monthly performance monitoring mechanism to evaluate key operational, commercial, and financial parameters has been implemented for all DISCOs.

The ECC also approved several technical supplementary grants for different ministries.