National Highway Authority has accelerated construction work on the Peshawar Northern Bypass project.
According to the details, twenty-five percent of the work on Charsadda Road Flyover, seventy-nine percent on Package-II, eighty-two percent on Package-III-A and seventy-five percent on Package-III-B has been completed.
Construction work on Package-I of Peshawar Northern Bypass has been fully completed.
The Peshawar Northern Bypass project is scheduled for completion by January 31 next year.