Friday, 20 December 2024, 10:41:46 pm


 
Suki Kinari Hydropower station construction exceeds 98 percent
February 29, 2024

The Suki Kinari Hydropower station’s overall construction progress has exceeded 98 percent.

The chairman and general manager of the project He Xiongfei said the project being completed under China-Pakistan Economic Corridor will significantly optimize Pakistan’s energy structure, boosting the country’s economic and social development.

Located in the Mansehra district of the Khyber Pakhtunkhwa province, the 884-megawatt hydropower project is being constructed by the Overseas Investment Company of China Gezhouba Group.

Once getting functional, the CPEC project will annually generate some 3.21 billion kilowatt-hours of clean electricity.